Productivity

Apollo Gold Corporation - Diamond Hill mine (U.S.A)

Primary Mining Method

Sub-Level Longhole retreat.
Information
  • Drilling with Cubex drill: approximately 152 m (500 ft) per shift.
  • Drilling with Boart drill: 91 m to 122 m (300 ft to 400 ft) per shift.
  •  Hauling (small stope): 454 t (500 short tons) per shift.
  •  Hauling (large stope): 1179 t (1300 short tons) per shift.
  •  Stope size: usually 4500 to 18 144 tons (5000 to 20000 short tons).

Coeur Silver Valley Inc. - Galena Mine (U.S.A)

Primary Mining Method

Cut-and-Fill mining method.
Information

2 miners per stope, 1 miner per face for 27 to 32 t (30 to 35 short tons) per manshift.


Echo Bay Minerals Co.- K-2 Mine (U.S.A)

Primary Mining Method

Sub-Level Longhole stoping.
Information
  • Mucking: 68 tons/hour (75 short tons/hour) with one scooptram and 3 trucks.
  • Drilling: 107 m/shift (350 ft/shift) with the Cubex drill.

Secondary Mining Method

Longhole transverse.
Information
  • Mucking: 68 tons/hour (75 short tons/hour) with one scooptram and 3 trucks.
  • Drilling: 107 m/shift (350 ft/shift) with the Cubex drill.

Hecla Mining Company - Lucky Friday mine (U.S.A)

Primary Mining Method

Overhand cut-and-fill.
Information

The productivity is:

  • Overall: 5 tons/manshift (6 short tons/manshift).
  • Underground tonnage: 12 tons/manshift (13 short tons/manshift).
  • Stope: 31 tons/manshift (34 short tons/manshift).

In order to achieve this productivity, two teams of 2 workers per stope and a nipper are working on rotating 10-hour shift. The teams assigned to a stope are responsible for the breakage, haulage to the orepass, remuck and stope preparation for the backfill.


Homestake Mining Co - Homestake Mine (U.S.A)

Primary Mining Method

Mechanized Cut-and-Fill.
Information

Productivity includes drilling, blasting and mucking: 8.16 tons/manhour (9 short ton/manhour).


Homestake Mining Co. - Darlot Mine (Australia)

Primary Mining Method

Sub-level long-hole retreat with backfill.
Information

Drilling: 115 m/day (377 ft/day).


Normandy Mining Ltd - Bronzewing mine (Australia)

Primary Mining Method

Open stope.
Information

Mining costs for December 2000:

  • $50/t (includes mining, development, hauling on surface).
  • Drilling: 100 m (328 ft) per shift.

Normandy Mining Ltd - Wiluna mine (Australia)

Primary Mining Method

Long-hole.
Information
  • Drilling: 200 m/shift (656 ft/shift).
  • Mucking: $6.50/ton + $1.25/ton for remote control mucking, price of the contractor.

WMC Resources Ltd - Leinster Nickel Operations (Australia)

Primary Mining Method

Longhole modified Avoca.
Information

Productivity for 1A zone is estimated at 10 000 tons/month.


WMC Resources Ltd - Miitel Mine (Australia)

Primary Mining Method

Modified Avoca.
Information

The following parameters were used in the productivity planning:

  • Two-boom Jumbo: 240 m/month (787 ft/month) for one single heading available and 260 m/month (853 ft/month) for multiple headings available.
  • Single boom Jumbo: 180 m/month (590 ft/month) for single or multiple headings, 1.5-m (5 ft) advances per day.
  • Raisebore: 40 m/month (131 ft/month) per hole.
  • Drilling and installation of cable bolt: 6000 m/month (19 685 ft/month).
  • Longhole raise: 15 m/week (49 ft/week) per slot.
  • Longhole drilling: 4500 m/month (14 764 ft/month).
  • Longhole production: 6000 tonnes per month per stope.